April 17, 2072- In the coming fiscal year (June 074) in the national transmission line 3 hundred and 58 MW of electricity will be added to domestic production has been. 6 MW of electricity from India during the same period to be imported.

According to an official of the Ministry of Energy on increasing domestic production within a year and can be imported from India during the rainy season due to additional electricity may be completely shedding in winter will only low-shedding. Recent demand for 13 MW of electricity is produced 8 hundred 2 9 MW (53 MW thermal plantasahita) only. Nepal reducing load-shedding import from India is around 3 hundred and 15 MW.

In the coming years, demand for electricity projected to reach 1 thousand 4 hundred and 23 MW of Electricity Authority. By then, the country focus on the construction of hydropower projects, 40 completed and 3 hundred and 58 megawatts of electricity it expanded and started.

According to the official, the private sector 38 projects will start production of up to 3 hundred and 14 MW of electricity if the electricity authority (the government) will be added to the building project, 44 MW of electricity. The NEA is constructing 30 MW and 14 MW project was the third Chameliya electricity production to start in the next mansirabatai Energy Secretary Suman Sharma said. The 40 projects total production of electricity became 8 hundred and 11 hundred and 87 MW 2 9 from the Ministry of Energy is expected.

Upcoming a year in additional 6 MW of electricity can be imported from India also Ministry officials said. Domestic production and import electricity from India will be the end of the rainy season in full-shedding.

According to the official Dhalkebar-Muzaffarpur transmission line 4 KV Substation construction and upgrading works Dhalkebar-INARUWA electricity transit will be completed within a year. Tyasamarphat additional 6 MW of electricity can be imported from India, the government solving the energy crisis and power development plan mentioned in the decade.

Dhalkebar-Muzaffarpur transmission line 220 kV substations will increase capacity Dhalkebar Authority is building. Construction will be completed in the next sub-dasainsamma. More 1 hundred 20 MW can be imported with what is. It would be more lightning dasaima relief will reach the public. To increase cross-border transmission line capacity 220 kV Substation kebhipachi Dhalkebar 4 hundred and Electricity Authority is planning a year banaisakne.

According to the Ministry of Energy the end of this year will be completed and start power generation projects of 50 MW Upper Marsyangdi A, Upper Media 25, the upper knife 22.2, a 14.9 heva opened, upper Mai 9.9 8 4.9 5 phava, Bhojpur 2. 48, opened jhyani 2, Daraudi opened 6, 3.2 geluna opened, opened sardi 4, 4 meeting opened, opened a dram 2.50, chyandi opened 2, 4.36 tunguna tsunami, mines opened 2, Mai Cascade 7, manayu 13, Thapa opened 11.20, Upper My C 5.1, 3.75 Dari opened, My little Cascade of 8 MW.

These projects will generate 2 hundred and 6 MW of electricity. However, due to the earthquake and sanctions, about nine months before the end of this year could be halted work by means of electricity generation projects to be started may take a further six months. Additional power output of these projects have been initiated for three maisahita, ministry officials said.

The project will be completed by the end of the fiscal year 2073/074 Upper Dordi A 22 MW, lower Modi, 20, opened phalamkhu 13.7, cake 2.83, 1.75 jumdi, theule 1.5, palm 5, Upper Mailung A 5, jogamai 7.6, 2.15 Upper Parajuli, lohore 4.2, midima karapu 3, rudi a 6.8, 3.33 kapadi Gadd, ghalemdi opened 4 and opened a 4 MW are puva. These projects will be 1 hundred and 6 megawatts of electricity.